  • Dollar variance is actual minus budget. Percent variance is the dollar variance divided by the budget.
  • Favorable means profit is better than budget. For revenue, above budget is favorable; for a cost, below budget is favorable.
  • A variance is a question, not an answer. The value is in the explanation: price, volume, timing or a one-off.
  • Set a threshold, explain everything above it every month, and update the forecast with what you learn.

What variance analysis is for

Variance analysis compares what actually happened in a period with what the budget said would happen, line by line, and then explains the gaps. Done well, it is the fastest monthly health check a firm has. It shows which parts of the plan held, which did not, and whether the misses are one-off timing or the start of a trend. In a project-based firm the timing question comes first: revenue follows milestones and billing runs, not the calendar, so a revenue miss is often work done but not yet billable, sitting in unbilled WIP. Done badly, variance analysis is a spreadsheet of red and green numbers that nobody reads and nothing changes. Run properly, it is a central routine in FP&A for project-based firms.

The comparison itself is simple arithmetic. The skill sits in two places: applying the favorable and unfavorable labels consistently, so readers can trust the table at a glance, and writing explanations that separate the four usual causes: price, volume, timing and one-offs. A variance caused by timing reverses next month. A variance caused by price or volume usually does not, and it belongs in the forecast immediately.

The two formulas

Dollar variance

Dollar variance = actual - budget. Keep this sign convention for every line, revenue and costs alike, and let the favorable or unfavorable label carry the judgement. Mixing conventions, such as budget minus actual for costs, is the most common reason variance tables confuse their readers.

Percent variance

Percent variance = dollar variance / budget x 100. The percent puts the dollars in proportion: a $6,000 miss on a $45,000 line is 13.3 percent and deserves a look, while the same $6,000 on a $500,000 line is 1.2 percent and usually does not. Watch one trap: when the budget figure is zero or very small, the percent explodes or is undefined. Report the dollars and mark the percent as not meaningful.

Favorable and unfavorable, stated plainly

Favorable means the variance improves profit versus budget. Unfavorable means it reduces profit versus budget. That is the whole rule, and it flips by line type. Revenue above budget is favorable; revenue below budget is unfavorable. A cost below budget is favorable; a cost above budget is unfavorable, even though the dollar variance is positive. Profit follows the same logic as revenue. If your table keeps the actual-minus-budget sign for dollars and adds an F or U label from the profit rule, any reader can check it in seconds.

Variances explain profit, not cashA month can beat its profit budget and still drain the bank account if customers pay slowly. The free cash conversion cycle calculator shows how long cash stays tied up in receivables and unbilled WIP.

Worked example: one month, six lines

Here is a fictional 40-person engineering firm reporting on a single month. Every figure below is invented, and every variance is calculated with the two formulas above.

LineBudgetActual$ variance% varianceF / U
Revenue$500,000$460,000-$40,000-8.0%U
Labor$180,000$198,000+$18,000+10.0%U
Subconsultant costs$150,000$138,000-$12,000-8.0%F
Rent$25,000$25,000$00.0%-
Other operating costs$45,000$51,000+$6,000+13.3%U
Total costs$400,000$412,000+$12,000+3.0%U
Profit$100,000$48,000-$52,000-52.0%U

Check the totals before reading the story. Budgeted costs of $180,000 plus $150,000 plus $25,000 plus $45,000 equal $400,000, and actual costs of $198,000 plus $138,000 plus $25,000 plus $51,000 equal $412,000. Budgeted profit is $500,000 minus $400,000, which is $100,000. Actual profit is $460,000 minus $412,000, which is $48,000. The profit variance of -$52,000 is exactly the sum of its parts: -$40,000 of revenue, -$18,000 of extra labor, +$12,000 saved on subconsultants, -$6,000 of extra other costs and nothing on rent. If your profit variance does not reconcile to the lines above it, the table has an error and the explanations built on it are worthless.

Now the explanations. Revenue missed by $40,000 because one large project reached its billable milestone in the first week of the next month instead of the last week of this one: a timing variance, which should reverse, with the work sitting in unbilled WIP meanwhile. Labor ran $18,000 over because project teams worked overtime to clear a backlog of deliverables: partly one-off, partly a warning that staffing is tight. Subconsultant costs came in $12,000 under budget after a renegotiated rate took effect: a price variance that repeats every month, so the forecast and possibly the budget assumptions should change. Other operating costs rose $6,000 on software renewals and travel: small dollars, but at 13.3 percent it is the largest percent variance in the table, which is why percent and dollars must be read together. Rent, a fixed cost, landed exactly on budget, as it should.

The management conclusion writes itself. Of the $52,000 profit miss, about $40,000 is timing and returns next month. The recurring items roughly offset: $12,000 of subconsultant savings against $18,000 of labor pressure and $6,000 of other costs. The action is not panic about profit; it is a staffing decision on labor and a forecast update that banks the subconsultant saving.

A monthly routine that keeps it useful

1. Set the threshold in advance

Explain every line that moves by more than, say, 5 percent and more than a fixed dollar amount. Below the threshold, skim. A threshold agreed in advance stops the monthly debate about which numbers matter.

2. Classify each big variance

Label it price, volume, timing or one-off. The label decides the response: timing needs patience, price and volume need forecast changes, and one-offs need nothing but a note.

3. Name an owner and a follow-up

Each explanation should end with what happens next and who owns it, even if the answer is "monitor for one more month." Variance analysis that never changes a decision is overhead.

4. Feed it into the forecast and the board pack

Recurring variances change the rolling forecast the same month they appear. The biggest two or three, with their explanations, belong on the first page of the board pack. This routine, run every month with the same discipline, is the core of our outsourced FP&A service.

Common questions

How do you calculate percent variance?

Divide the dollar variance by the budget figure and multiply by 100. If actual revenue is $460,000 against a $500,000 budget, the dollar variance is -$40,000 and the percent variance is -$40,000 divided by $500,000, which is -8.0 percent.

Is an unfavorable variance always bad?

No. Unfavorable only means worse than budget in profit terms. Spending more on labor because a large order landed early can be unfavorable and still be the right outcome. The label tells you where to look; the explanation tells you whether to worry.

How large does a variance need to be before I investigate it?

Set a threshold that combines size and proportion, such as more than 5 percent of the line's budget and more than a fixed dollar amount that matters to you. Investigate everything above the threshold, and skim the rest. Recheck the threshold once a year as the company grows.

Should variance analysis use the budget or the forecast?

Both, for different questions. Actuals versus budget shows whether the plan is being met. Actuals versus the latest forecast shows whether your expectations were right. Most monthly packs show actuals against budget, with the forecast updated for anything the variance revealed.

Keep reading

General information, not advice for your specific situation.

Rather have the analysis done for you?

Outsourced FP&A that closes the variance loop every month: budget vs actual, plain-English explanations, and a forecast updated for what the numbers revealed. From $2,500/month.

Scope your project

Prefer email? hello@mesfonic.com