Cash forecasting and FP&A for specialty and MEP contractors

See which jobs need cash before the next pay application clears.

A specialty or MEP contractor bills through a general contractor, waits behind the owner's payment, and runs a service department on a completely different clock in the same building.

How specialty and MEP contractors bill

Specialty and MEP contractors - mechanical, electrical, plumbing, fire protection, and similar trades - usually work as subcontractors. Project work bills by progress: a monthly pay application against a schedule of values, submitted to the general contractor, certified up the chain, and paid only after the owner pays the general contractor. Pay-when-paid terms are common, which puts the subcontractor last in line for its own money. Retainage is held on every payment, commonly 5 or 10 percent, until substantial completion of the subcontractor's work or of the whole project.

Alongside project work, most MEP firms run a service and maintenance operation that bills nothing like a project. Service calls bill on completion or weekly, maintenance contracts bill a fixed amount monthly or quarterly, and small quoted repairs bill on acceptance. The service side collects in days or weeks; the project side collects in months. One bank account funds both, which is why a firm can have a healthy service department and still be squeezed by its project book.

Where the cash gets stuck

The project side stacks three delays. First, work performed in a month waits for the pay application cycle to close. Second, the application waits for certification by the general contractor and the owner. Third, payment waits for the owner to pay the general, and the general to pay the sub. Weekly payroll for field crews runs through all three delays without pausing. Retainage then holds a slice of every dollar back for months after the work itself is finished, so growth in project volume automatically grows the amount of cash other parties are holding.

The service side has the opposite problem: it is easy to let it subsidise the project side without noticing. Service receipts arrive fast and feel like available cash, but they are already spoken for by service payroll, parts, and vehicle costs. A firm that reads one combined bank balance will systematically overstate how much room it has. The fix is to forecast the two sides separately - project receipts on their certified, retained, pay-when-paid timeline, service receipts on theirs - and only then combine them.

Worked example: one pay application under a general contractor

Fictional example. A fictional MEP contractor holds an $850,000 subcontract with 5 percent retainage. It had completed $340,000 of work before this period and completes another $170,000 this period. There are no stored materials.

ItemAmount
Work completed before this period$340,000
Work completed this period$170,000
Total completed to date$510,000
Retainage held to date (5% of $510,000)$25,500
Earned less retainage$484,500
Paid on previous applications ($340,000 less 5%)$323,000
Due on this application$161,500

The current payment, $161,500, is exactly this period's $170,000 of work less its $8,500 of retainage - and it arrives only after the owner pays the general contractor and the general pays the sub. Meanwhile $25,500 of the firm's earned money sits in retainage, growing by $8,500 with every similar period, and field payroll runs weekly throughout. The subcontract is profitable. The calendar is the problem, and it is a predictable one.

Try it in Excel: the free 13-week cash flow forecast template for Excel: receipts by customer or project, payroll and vendor runs, and a check that flags every week below your cash floor. No email or sign-up.

What cash forecasting and FP&A covers for specialty and MEP contractors

For a specialty or MEP contractor, project-based FP&A work means a rolling 13-week cash forecast that models project receipts on their real path - application, certification, owner payment, general contractor payment - with retainage tracked as its own balance by job, and the service department forecast separately on its faster cycle before the two are combined. Job profitability reporting compares each subcontract's billed and collected amounts against labor and material cost to date, so a job that looks fine on billings but is bleeding on collections is visible early. Working capital work focuses on application discipline: every dollar of completed work applied for every month, stored materials documented, and retainage release tracked as a receivable with a date, not a hope.

Free tools for this industry: the retainage calculator and the WIP over-under billing calculator.

Which service fits first

Start with a 13-week cash flow forecast, $2,900 fixed fee. Thirteen weeks covers several full pay application cycles: weekly field payroll out, certified applications collecting 45 to 75 days later, and retainage building in the background. Built week by week and split between project and service work, it shows exactly which weeks the project book squeezes the firm, and how large the credit line needs to be before the next large subcontract starts.