Fictional sample monthly FP&A pack

Fictional sample. Every figure on this page is fictional and illustrative. The company, the projects and the numbers are invented to show the format of the deliverable.

Monthly FP&A pack - fictional sample

Clearline Projects (fictional)

Fictional 32-person project firm, 22 billable staff
Reporting month: November 2026 (fictional)
Cash (fictional)$485k
Forecast margin (fictional)12.4%
Backlog (fictional)$1.56m
Utilization (fictional)75.0%

EAC by project (fictional)

Project (fictional)Contract valueCost to dateCost to completeEACForecast marginMargin %
Willow Creek Fit-Out$1,200,000$720,000$360,000$1,080,000$120,00010.0%
Northgate Systems Upgrade$900,000$410,000$340,000$750,000$150,00016.7%
Harbor Point Phase 2$750,000$500,000$200,000$700,000$50,0006.7%
Elm Street Renovation$600,000$180,000$300,000$480,000$120,00020.0%
Cedar Lodge Assessment$350,000$210,000$110,000$320,000$30,0008.6%
Total$3,800,000$2,020,000$1,310,000$3,330,000$470,00012.4%

EAC is cost to date plus cost to complete. Forecast margin is contract value minus EAC. Total margin: $470,000 divided by $3,800,000 is 12.4 percent.

WIP schedule summary (fictional)

Project (fictional)Revenue earnedAmount billedUnderbilled / (overbilled)
Willow Creek Fit-Out$780,000$720,000$60,000
Northgate Systems Upgrade$480,000$520,000($40,000)
Harbor Point Phase 2$540,000$500,000$40,000
Elm Street Renovation$210,000$190,000$20,000
Cedar Lodge Assessment$230,000$230,000$0
Total$2,240,000$2,160,000$80,000 underbilled

Retainage held by clients at month end: $148,000, included in amounts billed above and receivable on release. Backlog is contract value minus revenue earned: $3,800,000 minus $2,240,000 is $1,560,000 of signed work still to deliver.

Utilization and 13-week cash summary (fictional)

Key figures - fictional dataFictional sample
Billable hours2,640
Available hours3,520
Utilization75.0%
13-week low, W6$245k

Utilization is 2,640 billable hours divided by 3,520 available hours (22 billable staff at 160 hours) = 75.0 percent. The 13-week forecast starts at $485,000, totals $2,540,000 of receipts and $2,610,000 of payments, and ends at $415,000. The low point is week 6 at $245,000, which is $55,000 below the $300,000 cash floor; week 8 also closes below the floor at $295,000.

$000sW1W2W3W4W5W6W7W8W9W10W11W12W13
Receipts180140220160190120260180240200230170250
Payments-210-190-200-240-180-230-190-200-190-210-180-200-190
Ending cash455405425345355245315295345335385355415
Fictional sample - company, projects and every figure are invented for illustration.Sample

How to read this pack

The EAC table is the profit view: Harbor Point Phase 2 and Cedar Lodge Assessment finish below a 10 percent margin, so they get the management attention. The WIP summary is the billing view: the firm has earned $80,000 more than it has billed, and clients hold a further $148,000 of retainage. The cash summary is the timing view: even with $1,560,000 of backlog, weeks 6 and 8 fall below the cash floor because receipts land after payroll. A pack in this format is maintained monthly inside outsourced FP&A, from $2,500/month. See how we work for how the forecast behind it is built.