Capacity vs backlog calculator

Can the team actually deliver the backlog in the window? Backlog hours spread evenly over the delivery months, set against the team's available hours and its hours at target utilization, month by month. Runs in your browser; nothing is stored or sent.

Backlog hours vs team capacity
Hours of signed work still to deliver
Share of available hours planned for delivery work

The model spreads backlog hours evenly across the delivery window. Real projects bunch up, so treat an even-spread shortfall as a minimum problem, not the worst case. Our guide to capacity planning for your backlog covers how to phase the hours month by month once this first check flags a gap.

Results update as you type. A negative shortfall figure means headroom, not a gap.

Your capacity positionEstimate
Hours needed per month-
Hours available per month-
Utilization required-
Total shortfall (hours)-
Extra people needed at target-

Enter your numbers to see the result.

Worked example

Example with the default numbers: 9,600 backlog hours to deliver in 4 months, a team of 12, 140 available hours per person per month, and an 80% utilization target. The work needs 2,400 hours a month (9,600 divided by 4). The team offers 1,680 available hours a month (12 times 140), or 1,344 hours at the 80% target. Required utilization is 142.9%, which is not achievable. Over the window the team offers 6,720 hours against 9,600 needed, a total shortfall of 2,880 hours, or 720 hours a month. At the target utilization the plan needs about 9.4 more people (2,400 divided by 112 target hours per person is 21.4 people, against 12 on the team). These are example numbers, not your firm.

Common questions

How do I estimate backlog hours?

From the remaining work on each signed project: the hours still to deliver, estimated the same way cost to complete is estimated, project by project, then added together. If you only track backlog in dollars, divide by your average realized rate per hour to get a rough hours figure, and treat it as rough.

What counts as available hours per person per month?

Paid hours in the month minus holidays, vacation and expected sick time. Use the same basis every month. If training and internal meetings sit inside available hours, the utilization target must be set on that same basis or the comparison misleads.

Why compare against a utilization target as well as total hours?

Because nobody can bill every available hour. The target is the share of available time you plan to spend on delivery work. A plan that fits total hours but needs 100% utilization does not fit in practice; a plan that fits at the target has room for the non-billable work that still has to happen.

What are the options when there is a shortfall?

Four, usually in combination: add people, extend the delivery window, reduce or re-sequence scope, or accept a period of utilization above target with a named end date. What does not work is leaving the dates and the team unchanged and hoping productivity closes a gap this size.