Change order cash impact calculator

How much cash sits in change order work that is done but not yet approved or billed, how long it stays tied up, and what that amount means as days of revenue. Runs in your browser; nothing is stored or sent.

Your numbers
Approval, billing and payment terms after the work is approved
Used to size the tied-up cash as days of revenue

Results update as you type. Months are converted at 365 days per year.

Your change order cash impactEstimate
Cash already spent-
Days tied up so far-
Total days cash tied up-
Cash tied up, as days of revenue-

Enter your numbers to see the result.

How it works

Cash already spent is the change order value times the cost percent already spent on the work. That cash went out when the work was performed, so it has been tied up for the months since, converted at 365 days a year, and it stays out for the payment delay that follows approval. Dividing the tied-up cash by one day of revenue (annual revenue over 365) sizes it against the firm.

Worked example with the default numbers: $85,000 of unapproved change orders at 70% cost already spent means $59,500 of cash is out the door. The work was performed 3 months ago, about 91 days, and a 45-day wait after approval takes the total time cash is tied up to 136 days. At $6,000,000 of annual revenue, $59,500 equals about 3.6 days of revenue. These are example numbers, not your projects.

Want every unbilled dollar found and ranked?

Unapproved change orders are one pocket of trapped cash; unbilled work, retainage and slow collections are the others. A liquidity review sizes each one and ranks the moves by cash impact. $950 fixed fee, delivered in about a week.