Your overhead rate as a percent of direct labor, the multiplier it creates, and what that means for the loaded cost and break-even fee of one project. Runs in your browser; nothing is stored or sent.

Your numbers
Rent, admin salaries, insurance, software and other overhead
Labor charged directly to projects
The fee or direct-cost base quoted for that project

Results update as you type.

Your overhead rateEstimate
Overhead rate-
Overhead multiplier-
Loaded cost of example project-
Fee above or below break-even-

Enter your numbers to see the result.

How it works

The overhead rate is total indirect costs divided by direct labor cost. The multiplier is 1 plus that rate, and a project's loaded cost is its direct labor times the multiplier. That loaded cost is also the break-even fee: the lowest fee that covers the project's labor and its share of overhead, before any other direct costs and before profit.

Worked example with the default numbers: indirect costs of $600,000 over direct labor of $500,000 give an overhead rate of 120.0% and a multiplier of 2.20x. A project with $50,000 of direct labor carries $60,000 of allocated overhead, so its loaded cost and break-even fee are $110,000. Against a fee of $130,000, the project sits $20,000 above break-even. These are example numbers, not your rates.

Want overhead tracked by project, not just for the firm?

A single firm-wide rate hides which projects carry the firm and which ride on it. Outsourced FP&A builds loaded cost and margin reporting by project and role, then tracks whether realized rates hold. From $2,500/month.