Project profitability calculator

Where a project will land if nothing changes: estimated cost at completion, projected profit and margin, and the gap to your target margin. Runs in your browser; nothing is stored or sent.

Your numbers

Status rule: At or above target when the projected margin meets or beats the target; Within 2 pts of target when it is under the target by 2 points or less; Below target when it is more than 2 points under. The 2-point band is a display choice so small slips stay visible - set your own threshold when you review real projects.

Results update as you type.

Your projected resultEstimate
Cost at completion (EAC)-
Projected profit-
Projected margin-
Gap to target-
Status-

Enter your numbers to see the result.

Tracking more than one project?

The free project profitability tracker for Excel puts up to 30 projects on one page: EAC, margin vs target, over and under billing, and where the margin is leaking. No email or sign-up.

Worked example

Example with the default numbers: a contract of $850,000, cost to date of $390,000, cost to complete of $300,000 and a target margin of 20%. Estimated cost at completion is $690k ($390,000 + $300,000). Projected profit is $160k and the projected margin is 18.8%. Target profit is $170k, so the gap to target is -$10k. Because 18.8% is 1.2 points under the 20% target, the status is Within 2 pts of target - still $10k short of target profit. These are example numbers, not your project.

Common questions

What is estimated cost at completion?

Estimated cost at completion, or EAC, is cost to date plus your best current estimate of cost to complete. It is the total cost you expect when the project finishes, and it changes every time the cost-to-complete estimate changes.

Why use cost to complete instead of percent complete?

Percent complete can hide trouble when early work was cheaper than later work. A cost-to-complete estimate forces a fresh look at what is left, which is where overruns usually sit.

What should I do when a project is below target?

First check the cost-to-complete estimate for missing scope, rework and rate changes. Then look at change orders for work already done but not yet priced. Closing even part of the gap early is easier than recovering it at the end.

How often should I update this?

Monthly at a minimum, and at every scope change. The point of the calculation is to see margin drift while there is still time to act on it.