What it is
Backlog is the stock of future work already under contract. For each open job, it is the contract value minus the revenue earned to date. Added across all jobs, it tells you how much contracted revenue is still ahead of you. It is one of the clearest forward-looking numbers a project business has, because unlike a sales pipeline, backlog is signed work, not hoped-for work.
Backlog answers practical questions. How many months of work are already won at the current pace? Can the business absorb a slow quarter of new sales without cutting staff? Is growth real, in the sense that earned revenue is being replaced by new contract value faster than it is being worked off? A business can post a strong revenue month and still be weakening, if backlog fell sharply while revenue rose.
The formula
Stated plainly: backlog equals total contract value of open jobs minus total earned revenue to date on those jobs. Earned revenue comes from the work in progress schedule, using percent complete applied to contract value. Only include signed contracts and approved change orders. Verbal promises, letters of intent that are not contracts, and pipeline prospects belong in a sales forecast, not in backlog, or the number stops meaning anything.
A useful companion figure is months of backlog: backlog divided by average monthly earned revenue. It translates a dollar stock into time, which is how staffing and hiring decisions are actually made.
How to calculate it
Take the work in progress schedule at month end. For each open job, subtract earned revenue to date from the current contract value, including approved change orders in both figures consistently. Add the remainders. Then check the movement: opening backlog, plus new contracts signed, minus revenue earned in the period, should equal closing backlog. If it does not reconcile, a job was added, removed or revalued without being recorded, and the schedule needs fixing before the number is used.
Worked example
Example - fictional numbers. A business has three open jobs at month end.
| Job | Contract value | Earned to date | Backlog |
|---|---|---|---|
| A | $500,000 | $200,000 | $300,000 |
| B | $400,000 | $150,000 | $250,000 |
| C | $300,000 | $100,000 | $200,000 |
| Total | $1,200,000 | $450,000 | $750,000 |
Step by step: for Job A, $500,000 minus $200,000 equals $300,000. For Job B, $400,000 minus $150,000 equals $250,000. For Job C, $300,000 minus $100,000 equals $200,000. Add them: $300,000 plus $250,000 plus $200,000 equals $750,000 of backlog. The totals check the same way: $1,200,000 of contract value minus $450,000 earned equals $750,000 still to be performed and earned.
Why it matters and common mistakes
Backlog matters because it sets the runway for revenue and staffing. Falling backlog is an early warning that arrives months before falling revenue, while there is still time to sell, sequence work or adjust hiring. Rising backlog with flat capacity is also a warning, of a different kind: start dates slip, clients wait, and delivery quality comes under pressure.
Common mistakes include counting unsigned work, forgetting to remove canceled jobs, leaving earned revenue stale so backlog is overstated, and reporting backlog without its expected timing. A dollar of backlog starting next month and a dollar starting next year are not the same for planning. Keep a simple split by expected start or by quarter. Backlog sits naturally beside the WIP schedule guide, and its cash timing can be modeled in the free 13-week cash flow calculator.
For turning that stock of signed work into a revenue forecast, see the guide to backlog to revenue conversion.
General information, not advice for your specific situation.
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.