The short version
- A WIP (work in progress) schedule lists every open job with its contract value, costs to date, estimated total cost, percent complete and billings to date.
- Percent complete times contract value gives earned revenue: the revenue the job has actually earned so far.
- Billings ahead of earned revenue are overbilling. Billings behind are underbilling. The difference is a balance sheet item, not profit.
- Banks and sureties read the WIP schedule before they read almost anything else. So should you, monthly.
- This guide is the how-to explainer for the WIP schedule itself and for over and under billing: what each column means, how each figure is calculated, and how to run the monthly review.
What a WIP schedule is
Contractors and other project firms earn revenue as work progresses, but they bill on a separate rhythm set by pay applications and invoices. The WIP schedule is the report that reconciles the two. For every open job it lines up what the contract is worth, what the job has cost so far, what it is expected to cost in total, how complete that makes it, how much revenue it has therefore earned, and how much has actually been billed. The gap between the last two numbers is the over or under billing position, and it is where the schedule earns its keep.
The WIP schedule also drives the accounting. Under percentage-of-completion accounting, revenue is recognized from the schedule, not from invoices, and the over and under billing totals land on the balance sheet: overbillings as a liability (billings in excess of costs and earnings), underbillings as an asset (costs and earnings in excess of billings). If your monthly financial statements show construction revenue, a WIP schedule sits underneath them whether you look at it or not.
The five inputs, job by job
- Contract value. The current contract amount, including approved change orders only. Unapproved change work does not belong in this number.
- Cost to date. All job costs incurred so far: labor, materials, subcontracts, equipment and job-specific overheads, on the same basis every month.
- Estimated total cost. Cost to date plus the honest estimate of cost to complete. This is the most judgement-heavy number on the schedule and the one that decides whether the schedule tells the truth.
- Percent complete. Cost to date divided by estimated total cost. The cost-to-cost method: simple, standard, and only as good as the estimate in the denominator.
- Billings to date. Everything invoiced on the job so far, from the billing system, not from memory.
From those five, two calculations follow. Earned revenue is percent complete times contract value. Over or under billing is billings to date minus earned revenue: positive means overbilled, negative means underbilled.
Worked example: three jobs
Here is a small fictional WIP schedule for a contractor with three open jobs. All figures are invented; the arithmetic is the standard calculation.
| Job | Contract value | Cost to date | Est. total cost | % complete | Earned revenue | Billings to date | Over / (under) |
|---|---|---|---|---|---|---|---|
| Job A | $600,000 | $270,000 | $450,000 | 60% | $360,000 | $390,000 | $30,000 |
| Job B | $350,000 | $140,000 | $280,000 | 50% | $175,000 | $150,000 | ($25,000) |
| Job C | $900,000 | $495,000 | $660,000 | 75% | $675,000 | $630,000 | ($45,000) |
| Total | $1,850,000 | $905,000 | $1,390,000 | $1,210,000 | $1,170,000 | ($40,000) |
Job by job: Job A is 270,000 / 450,000 = 60 percent complete, so it has earned 60 percent of $600,000, which is $360,000. It has billed $390,000, so it is overbilled by $30,000: billings are $30,000 ahead of earned revenue. That is a contract liability on the balance sheet, and it helps cash only once those invoices are collected. Job B is 140,000 / 280,000 = 50 percent complete and has earned $175,000 against billings of $150,000, so it is underbilled by $25,000. Job C is 495,000 / 660,000 = 75 percent complete, has earned $675,000, and has billed $630,000, so it is underbilled by $45,000. Across the portfolio, earned revenue of $1,210,000 against billings of $1,170,000 leaves the company net underbilled by $40,000: on balance, $40,000 of earned work has not been billed yet - work the company carries until it can invoice. That is arithmetic across jobs, not a measured cash outflow; collections are a separate question.
A note on method. This is the simplified cost-to-cost approach. How revenue is recognized in your financial statements depends on your contracts and accounting policies - under ASC 606, over-time recognition and the input method have conditions, and items such as uninstalled materials or unusual waste may need adjusting. Approved change orders are a conservative input here, not a universal rule. Your controller or CPA decides the statement treatment; the schedule above is for managing jobs and cash.
What overbilling really means
Overbilling feels like strength. Cash arrived ahead of the work; the bank balance looks healthy. But the overbilled amount is not profit and it is not spare cash: it is work you owe. The costs of performing that work are still ahead of you, while the billings that would normally fund them have already been collected and, in most companies, already spent. A job that stays heavily overbilled into its final third will bill thin at the end while costs run at full rate - the pattern behind the contractor who is busy, profitable on paper, and suddenly short of cash on a nearly finished job. Deliberate front-loading of a schedule of values creates the same shape on purpose, which is why the WIP schedule, not the bank balance, is the honest measure. For the cash side of this, see cash flow forecasting for construction companies and retainage and cash flow.
What underbilling really means
Underbilling is the mirror image: you have performed and paid for work you have not yet billed. Some is innocent - billing runs monthly, so a job is always partly unbilled mid-cycle. Persistent underbilling is different. It can mean applications are going out late or understated, that stored materials or change work are sitting unbilled, or that costs are running ahead of estimate and the percent complete is overstated, in which case the earned revenue itself is too high and a margin fade is hiding inside the schedule. Underbilled work also lengthens the whole cash cycle: the work-to-cash gap measured by the cash conversion cycle calculator gets longer by exactly the time work sits performed but unbilled. Our guide to unbilled revenue and WIP covers how to age and chase that balance.
Why banks and sureties read it first
A lender or surety underwriting a contractor wants to know three things the P&L cannot tell them: whether reported margins are real, whether billings are running ahead of progress, and whether any job is quietly heading for a loss. The WIP schedule answers all three. Gross profit to date by job exposes fading margins while there is still time to react. A portfolio that is heavily overbilled in total tells the reader that future billings are already spoken for. And because percent complete rests on estimated total cost, a schedule where estimates never change, even on troubled jobs, tells the reader the numbers are being carried rather than managed. This is why bonding and credit reviews ask for the WIP schedule by name, and why the pack you send them matters: a clean, current schedule with honest estimates is a credit asset. Presenting it well is part of board and lender reporting done properly.
Using the WIP schedule to forecast cash
The schedule feeds the cash forecast directly. Earned revenue not yet billed becomes future billings on your normal application cycle; billings become receipts on each payer's normal payment lag; the overbilled balance warns you that late-job billings will run below late-job costs. Feed those three flows into a weekly forecast - the method in cash flow forecasting for project-based businesses - and the WIP schedule stops being a compliance report and becomes the earliest warning system a project firm has.
Common questions
Is overbilling good or bad?
Neither, in small and stable amounts. Overbilling means billings are ahead of the work, which helps cash only when those invoices are collected. It becomes a problem when it grows: the cash is spent, but the work it was billed for still has to be performed and paid for later, out of thinner billings at the end of the job.
Is underbilling always a problem?
No. Small underbilling early in a job is common and usually just means billing lags progress by a cycle. Persistent or growing underbilling is a warning: either billing discipline is weak, or costs are running ahead of the plan and the percent complete is flattering the job.
How often should a WIP schedule be updated?
Monthly, at minimum, and before any meeting with a bank or surety. The estimated total cost on each job should be re-confirmed by the person running the job every month, not carried forward by default.
What does a bank do with the WIP schedule?
It checks whether reported profit is backed by progress, whether billings are running ahead of earned revenue across the whole portfolio, and whether any single job shows a fading margin or a loss. It is one of the fastest ways a lender can judge the quality of a contractor's numbers.
Try it in Excel: the free project profitability tracker for Excel: estimate at completion, margin against target, over and under billing and margin leakage for up to 30 projects. No email or sign-up.
Keep reading
Free project profitability tracker (Excel)
Over and under billing by project, alongside EAC and margin vs target.
IndustryConstruction
Monthly pay applications and retainage on every payment, against payroll that runs every single week.
GuideCash flow forecasting for project-based businesses
GuideCash flow forecasting for construction companies
GuideRetainage and cash flow
GuideUnbilled revenue and WIP
GuideUtilization rate and cash flow
Free toolCash conversion cycle calculator
General information, not advice for your specific situation.
Send your bank a pack that answers its questions
Board and lender reporting that includes a current WIP schedule, a 13-week cash view and the variances explained, every month. From $1,500/month.
Prefer email? hello@mesfonic.com
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.