Retainage is the percentage of each progress billing the customer holds back and pays only when the job is complete.

What it is

Retainage, also called retention, is money you have earned but do not receive yet. On each progress billing the customer pays most of the amount and holds back a fixed percentage set in the contract. The held money acts as security that the work will be finished, defects corrected and required paperwork delivered. It is released under the conditions the contract sets, commonly at or after substantial completion.

On the balance sheet, retainage sits as a receivable, but it is not like an ordinary invoice. An ordinary invoice is due on payment terms. Retainage is due when conditions are met, which can be months after the work itself. That is why it is tracked separately, by job and by customer, with its own expected release date.

The formula

Stated plainly: retainage held on a billing equals the billing amount multiplied by the retainage rate. Retainage held to date equals total billings to date multiplied by the rate, where the rate is constant. Cash paid on a billing equals the billing minus the amount held. If the contract steps the rate down partway through, or caps the total held, calculate each billing under the term that applies to it rather than applying one rate to the whole job.

How to calculate it

Take each progress billing in turn. Multiply it by the contract rate. Add the held amounts together for the running balance. Then check that balance against the customer statement or pay application, because a customer applying a different rate, or holding on change orders you expected to be exempt, is easier to catch on the second billing than at release. Record the release trigger beside the balance: substantial completion, a certificate, a punch list cleared, or a date, so the forecast uses the real trigger and not a hope.

Worked example

Example - fictional numbers. A job is billed in three progress billings of $200,000, $250,000 and $150,000. The contract retainage rate is 10 percent throughout.

BillingAmount billedHeld (10%)Held to dateCash paid (90%)
1$200,000$20,000$20,000$180,000
2$250,000$25,000$45,000$225,000
3$150,000$15,000$60,000$135,000
Total$600,000$60,000-$540,000

Step by step: first, add the billings: $200,000 plus $250,000 plus $150,000 equals $600,000 billed to date. Second, apply the rate to each billing: 10 percent of $200,000 is $20,000, of $250,000 is $25,000, and of $150,000 is $15,000. Third, add the held amounts: $20,000 plus $25,000 plus $15,000 equals $60,000 held to date. Fourth, cash paid is $600,000 minus $60,000, which equals $540,000. The remaining $60,000 arrives only when the release conditions are met.

Why it matters and common mistakes

Retainage matters because costs are paid in full while revenue arrives short. On a long job the held balance can grow larger than the profit on the job, so a profitable business can still run short of cash. It also stacks across jobs: several modest held balances can add up to a very large amount of cash sitting with customers.

Common mistakes include forecasting the release in the week the job finishes rather than the week the customer will actually pay after approval, forgetting retainage held on change orders, and never aging old held balances after completion. Track retainage like receivables, with an owner and a follow-up date for anything past its trigger. The deeper guide is retainage and cash flow, and the free retainage calculator shows the held balance on your own contract numbers.

General information, not advice for your specific situation.