The short version
- Retainage is the share of each progress billing the customer holds back until the job is done, usually 5 to 10 percent.
- It builds quietly month by month and often ends up larger than the profit on the job.
- Release depends on substantial completion, the punch list and paperwork, not just on finishing the work.
- Forecast the release in the week you realistically expect the money, and don't count it before the contract's release terms are met - which may allow partial or step-down releases before final completion.
What retainage is
Retainage, sometimes called retention, is money you have earned but do not get yet. On each progress billing, the customer pays most of the invoice and holds back a fixed percentage. The held amount is security: it gives the customer leverage to make sure the work is finished, defects are fixed and paperwork is delivered. You carry it on the balance sheet as retainage receivable, separate from ordinary accounts receivable, because it follows different rules and a different clock.
The cash problem is timing. Your costs on a job - labor, materials, equipment, subcontractors - are paid in full and on time. Your revenue arrives with a piece missing. On a long job the missing piece grows every month, and the business funds the gap out of its own cash or its credit line. Companies rarely feel this in month one. They feel it in month five, when several jobs are running at once and the held balances have stacked up.
How it builds across a job
Retainage builds in proportion to billings, so it tracks the shape of the job. Slow start, heavy middle, taper at the end: the held balance follows the same curve. Because it is a percentage of cumulative billings, the balance only ever grows until release. Nothing about normal progress reduces it. A job that bills evenly still adds the same percentage every single month, which is why the total surprises people. Ten percent sounds small on one invoice. Ten percent of everything you have billed this year is a large amount of money sitting in someone else's account.
It also stacks across jobs. Three jobs at different stages can each look manageable while the combined held balance equals a month of payroll. Track retainage as one portfolio number, by customer and by expected release date, not just job by job.
A worked example
Take a fictional job with a contract value of $1,200,000 and retainage of 10 percent, billed over six months. The billings, the amount held each month and the running balance look like this:
| Month | Billed | Held (10%) | Held to date | Cash paid (90%) |
|---|---|---|---|---|
| 1 | $150,000 | $15,000 | $15,000 | $135,000 |
| 2 | $200,000 | $20,000 | $35,000 | $180,000 |
| 3 | $250,000 | $25,000 | $60,000 | $225,000 |
| 4 | $250,000 | $25,000 | $85,000 | $225,000 |
| 5 | $200,000 | $20,000 | $105,000 | $180,000 |
| 6 | $150,000 | $15,000 | $120,000 | $135,000 |
The billings add to $1,200,000, the full contract value. The customer pays 90 percent of each billing, $1,080,000 across the job, and holds $120,000 in total. That $120,000 arrives only at release, after completion. Notice what it means mid-job: at the end of month 4 the company has billed $850,000 and received $765,000, while its costs have been paid in full. If the job earns a 10 percent margin, the entire expected profit is $120,000 - exactly the amount held. Until release, the company has done the work, carried the cost and kept none of the profit in cash.
Typical percentages and terms
Five to ten percent is the common range, and ten percent is the most common starting point. Some contracts step the rate down - for example, 10 percent until the job is half billed, then 5 percent after that - and some cap the total held at a fixed amount. Public work sometimes follows a rate set by rule rather than by negotiation. The terms that matter most are easy to miss at signing: the exact percentage, whether it steps down, what triggers release, and what documents release requires. Read those clauses before the first billing, not at the end of the job when the money is already held.
When retainage releases
Release usually follows substantial completion: the point where the work is complete enough for its intended use, even if small items remain. After that comes the punch list, the short list of fixes and finishes the customer requires before final payment. Clearing it quickly is worth real money, because the held balance often dwarfs the cost of the remaining items.
Paperwork gates release as often as physical work does. Lien waivers, warranties, closeout documents, final inspections and signed acceptances are common requirements, and a missing document holds the whole amount, not a share of it. On subcontract work there is a second gate: a pay-when-paid chain. Your customer may not release your retainage until the owner releases theirs, so your cash date depends on a chain of approvals above you. Ask where your job sits in that chain and what the owner requires, because that, not your own completion date, often sets the real timeline.
Partial releases exist on some contracts - at set completion stages, or for portions of the work accepted early - but they are granted by the contract, not by asking. If the contract is silent, plan on one release at the end.
One balance, three cash assumptions
Split the held balance by where each amount stands: still held, submitted for release, and approved with an expected payment date. Fictional example: of $170,000 held across four jobs, $60,000 has an approved payment date, $50,000 has been submitted without confirmation, and $60,000 is still waiting on closeout.
Put the approved $60,000 in its expected clearing week. Give the submitted $50,000 an explicit timing assumption and a later-payment case. Leave the remaining $60,000 out of payroll coverage, even if the job is substantially complete. Where a release date is unconfirmed, mark it as unconfirmed: the contract, project status and applicable rules decide when release is due, and management and its counsel decide how to pursue it.
Forecasting retainage in a 13-week model
Inside a weekly cash forecast, retainage needs its own line, separate from ordinary receipts. Build it in three steps. First, list every job with a held balance, the amount held and the contract release trigger. Second, place each expected release in a specific week based on where the job really is: punch list progress, paperwork status and the customer's normal payment cycle after approval. A release approved this week usually still pays on the customer's next payment run. Third, keep everything else out. Retainage on jobs still in progress does not enter the 13 weeks at all unless completion falls inside the window.
Be conservative with the week you choose. If substantial completion is expected in week 9 and the customer pays monthly, the cash may land in week 12 or 13, not week 9. Modeling it early creates a false cushion in the middle weeks, which is exactly where a forecast does its damage. This is the kind of line-by-line judgment a 13-week cash flow forecast is built around: each receipt placed by how that customer actually behaves.
When a release slips
Releases slip for ordinary reasons: a slow inspection, a disputed punch item, a waiver sent to the wrong place. Treat a slipped release like any other late receipt. Move it in the forecast the moment you hear about it, follow up in writing, and keep the paperwork file complete so nothing waits on you. And track the aging of held balances the way you track receivables: anything held long past completion deserves a named owner and a weekly follow-up, because nobody upstream is watching it for you.
Common questions
Is retainage revenue?
Yes. Revenue follows your recognition policy for the work performed; the amount withheld is typically carried separately on the balance sheet - as a contract asset while release is conditional, and a receivable once it is unconditional. It is not cash until the customer releases it, which is why profitable jobs can still strain the bank account.
What is a typical retainage percentage?
Five to ten percent of each progress billing is common, and ten percent is the most common starting point. Some contracts reduce the rate partway through the job, and some cap the total held. The contract, not habit, sets the number.
When does retainage get released?
Usually at substantial completion, after the punch list is cleared and the paperwork the contract requires is delivered. On subcontract work, your release often waits on the owner releasing the contractor above you, so the chain matters as much as the date.
Should retainage go in a cash flow forecast at face value?
Place it in the week you realistically expect payment, not the week the contract says it is due, and keep it out of the weeks before substantial completion entirely. If the date is uncertain, model a later week and treat an early release as upside.
Try it in Excel: the free 13-week cash flow forecast template for Excel: receipts by customer or project, payroll and vendor runs, and a check that flags every week below your cash floor. No email or sign-up.
Keep reading
Construction
Monthly pay applications and retainage on every payment, against payroll that runs every single week.
GuideWIP schedules and over and under billing
GuideUnbilled revenue and WIP
GuideCash flow for construction companies
General information, not advice for your specific situation.
Rather have it built for you?
A 13-week cash flow forecast built on your real numbers, with retainage releases placed in the weeks they are actually likely to land. $2,900 fixed fee.
Prefer email? hello@mesfonic.com
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.