WIP schedule

A WIP schedule is the monthly list of open jobs showing contract value, costs, percent complete, earned revenue and billing position.

What it is

WIP stands for work in progress. A WIP schedule is the control sheet for a project business: one row per open job, updated monthly, showing the contract value, costs incurred, the estimate at completion, percent complete, revenue earned, amounts billed, and whether each job is over billed or under billed.

Without a WIP schedule, revenue on long jobs is guesswork and margin problems hide until close-out. With one, reviewed honestly each month, you can see which jobs are drifting, which are funding the business and which are quietly consuming cash, while there is still time to act.

The core calculations

Percent complete equals cost incurred to date divided by estimate at completion. Earned revenue equals percent complete multiplied by contract value, including approved change orders. Over or under billing equals earned revenue minus billings to date. Each result depends on the estimate at completion being current.

Worked example

Example - fictional numbers. A schedule at month end holds two open jobs, A and B.

JobContractCost to dateEAC% completeEarnedBilledPosition
A$500,000$200,000$400,00050%$250,000$240,000$10,000 under billed
B$300,000$180,000$200,00090%$270,000$285,000$15,000 over billed

Step by step for Job A: $200,000 divided by $400,000 equals 50 percent complete, and 50 percent of $500,000 equals $250,000 earned. Earned $250,000 minus billed $240,000 leaves Job A $10,000 under billed. Job B is 90 percent complete, with $270,000 earned against $285,000 billed, so it is $15,000 over billed.

The full method, with worked examples: WIP schedule: over and under billing explained

For a single job, the free WIP over and under billing calculator runs the percent complete and earned revenue math for you.