Anatomy of a cash crunch: the fixed-fee overrun
A fictional fixed-fee job eats its margin first and its cash second, and the fade in its EAC margin is visible months before either runs out.
Last updated: November 2026
Fictional story. This case is fictional. The firm, the project, the client and every figure are invented to show how a cash crunch builds and which signal exposes it early. No real company is described.
The setup
Alder & Vine Interiors (fictional) is an 18-person firm that wins work on fixed fees. Its flagship job in this fictional case is a fit-out priced at a fixed fee of $480,000. The fee was built from a budget cost of $384,000, which left a target margin of $96,000, or 20 percent of the fee. The fee does not move when costs move. That is the deal the client bought, and it is a good deal for the firm as long as the budget holds: the margin is larger than on its cost-plus work, and the client gets certainty. The risk sits entirely on one side of the table. Every dollar of cost above $384,000 comes straight out of the $96,000 margin, and once the margin is gone, every further dollar comes out of cash the firm has already counted as its own.
At signing, the budget looked sound. Labor was estimated from the firm standard rates, the two main bought-in packages were quoted, and a contingency sat inside the budget for the unknowns that fit-out work always contains. The project manager was experienced, the client was decisive, and the first month ran close to plan. Nothing in the setup suggests a problem job. That is worth stating plainly, because fixed-fee overruns rarely start as problem jobs. They start as normal jobs whose remaining cost is estimated with slightly too much hope, month after month, until the hope runs out.
The numbers moving
The firm reviewed the job monthly using estimate at completion: cost to date plus a bottom-up estimate of cost to complete. The sequence across four monthly reviews was:
| Review (fictional) | Cost to date | Cost to complete | EAC | Forecast margin on $480,000 fee |
|---|---|---|---|---|
| Month 1 | $95,000 | $295,000 | $390,000 | $90,000 (18.8%) |
| Month 2 | $180,000 | $240,000 | $420,000 | $60,000 (12.5%) |
| Month 3 | $255,000 | $220,000 | $475,000 | $5,000 (1.0%) |
| Month 4 | $310,000 | $210,000 | $520,000 | -$40,000 (-8.3%) |
Each row ties: cost to date plus cost to complete equals EAC, and the $480,000 fee minus EAC equals the forecast margin. The final position is an EAC of $520,000 against a budget of $384,000 - an overrun of $136,000. The margin did not fall off a cliff in month 4. It faded: $90,000, then $60,000, then $5,000, then negative. Behind the fade were three ordinary causes. A wall condition nobody could see at pricing added labor and material. The client requested changes that the team delivered as goodwill before anyone priced them as change orders, so the fee stayed fixed while the scope quietly grew. And the closing phase - snagging, rework and final documentation - was estimated in month 1 at a figure borrowed from an easier job, and it stayed borrowed long after the job itself had shown it would cost more.
The cash followed the margin with a lag, which is what makes this pattern dangerous. Through months 1 to 3 the job still billed on its fixed schedule and the bank balance looked acceptable. The overrun spent cash on labor and packages in months 2, 3 and 4, while the fee receipts stayed exactly as planned. By the time the job closed, the firm had spent $520,000 to earn $480,000, and the $40,000 loss plus the working capital absorbed along the way had pulled its cash from $210,000 to $118,000, squeezing two unrelated, healthy jobs whose payroll the same account funds.
The signal that caught it
The signal was EAC margin fade. Not the month 4 loss itself - by then the money was mostly spent - but the pattern across months 1 to 3: the forecast margin fell at every review, and the cost to complete never fell as fast as cost to date rose. Between months 1 and 2, the firm spent $85,000, yet cost to complete dropped by only $55,000, so EAC rose $30,000. Between months 2 and 3 it spent $75,000 and cost to complete dropped by only $20,000, so EAC rose $55,000. A healthy job consumes its to-go estimate as it spends. A fading job replaces spent money with newly discovered work. Two consecutive months of fade is a signal with a name, a size and a direction, and it arrived in month 2, when roughly $240,000 of spending was still in front of the firm and still manageable.
What the firm did
Because the fade was named in month 3 at the latest, the firm still had moves. It priced the client changes properly from that point: every further request got a written change order with a fee attached before work started, and two already-delivered changes were documented and negotiated into a $25,000 fee increase, lifting the fee to $505,000 and cutting the forecast loss from $40,000 to $15,000. It re-sequenced the closing phase, putting its most experienced finisher on the snagging list instead of the cheapest available hands, which cut the rework allowance inside cost to complete. And it changed its own rule for every fixed-fee job that followed: cost to complete must be re-estimated bottom-up each month by the person doing the work, any job whose margin fades two months in a row goes to the top of the review, and contingency is reported as its own line so nobody can spend it silently.
The job still lost money. Signals do not repeal arithmetic, and a fixed fee means the firm, not the client, owns the overrun. But the loss closed at $15,000 instead of growing past $40,000, cash stayed above the floor throughout, and the pricing of the next three fixed-fee bids carried the lesson in their allowances. The margin went first, quietly, in a forecast column. The cash would have followed loudly, in the bank account, a quarter later. Watching the first number is how the firm avoided being surprised by the second.
The free project profitability calculator works through the same five numbers for one project: contract value, cost to date, cost to complete, EAC and forecast margin. Keeping those numbers current on every job, every month, is core work inside outsourced FP&A.
Try it in Excel: the free project pricing calculator template for Excel: cost each role and expense by month, price to a target margin, and see the peak cash the deal needs before it pays. No email or sign-up.
Keep reading
Anatomy of a cash crunch - all four cases
OverviewProject-based FP&A
Free toolProject profitability calculator
ServiceOutsourced FP&A
General information, not advice for your specific situation. This story is fictional.
Rather have it built for you?
A 13-week forecast and monthly reporting that flag the low week while there is still time to act.
Prefer email? hello@mesfonic.com
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.