A cash forecasting and FP&A service for an architecture firm runs the firm's forward numbers: a rolling cash forecast built from phase billing, project margins tracked phase by phase, utilization by person and team, and backlog converted into expected revenue. A design fee arrives in phases, but payroll does not, so unbilled work, uneven phase effort, and one over-running phase decide whether the cash holds.

What cash forecasting and FP&A covers for architecture and design firms

For an architecture and design firm, project-based FP&A work means a rolling 13-week cash forecast built from phase billing schedules and real client payment behavior, monthly reporting that compares fees billed against work performed on every live project, and project profitability tracked phase by phase so an over-running phase is visible while there is still fee left to manage. Working capital work focuses on unbilled work: time recorded but not yet invoiced, phases drawn ahead of the work they still have to fund, and consultant pass-through costs the firm pays before the client pays it. The aim is simple - no phase should surprise the bank account months after the hours were worked.

Free tools for this industry: the net multiplier calculator and the project profitability calculator.

How architecture and design firms bill

Architecture firms usually work for a fixed fee, or a fee set as a percentage of construction cost, and bill it in phases that follow the design process. A common sequence is pre-design, schematic design, design development, construction documents, and construction administration, with each phase assigned a share of the total fee in the contract. The firm invoices as a phase progresses or completes, often monthly against the percent of the phase it judges complete. A $480,000 fee is therefore not one payment; it is five pools of money, earned at different speeds over a project that may run two years.

Two features make this harder than it looks. First, effort does not follow the fee split evenly. Construction documents typically carry the largest fee share and the heaviest production hours, and a difficult project can consume far more hours in one phase than the phase fee assumed. Second, construction administration stretches: the fee is fixed, but the phase lasts as long as construction lasts, through delays the design firm does not control. Consultants - structural, mechanical, and other engineers engaged by the architect - add a pass-through layer, billed to the client through the architect's invoice and paid by the architect on their own schedule.

Where the cash gets stuck

Unbilled work is the main reservoir. Studios track time by project and phase, but time only becomes an invoice when someone reviews it, agrees the percent complete, and bills it. Work performed in a phase that is nearly exhausted poses a worse question: bill the remaining fee now and have nothing left to bill while the phase continues, or keep working and let unbilled time pile up. Either way, payroll for designers and project architects runs every two weeks, while phase invoices go out monthly and clients - owners and developers - pay in 30 to 60 days.

Fee drawdown against percent complete creates a slow, quiet risk. If a firm bills percent complete generously early in a phase, cash looks fine while the remaining fee shrinks below the remaining work. The end of the phase then arrives with hours still to work and little or nothing left to invoice. Add a project that pauses after design development - a common event when financing or permits stall - and the firm has delivered most of its billable phases, holds a receivable, and has a team to redeploy with no construction administration phase starting on schedule.

Worked example: a fixed fee drawn down by phase

Fictional example. A fictional design firm holds a $480,000 fixed fee split by phase as below. Its construction documents phase carries a budget of 1,280 hours at a blended rate of $150 an hour. The team actually works 1,520 hours in that phase, and the loaded cost of those hours is $95 an hour.

PhaseShare of feeFee amount
Pre-design5%$24,000
Schematic design15%$72,000
Design development20%$96,000
Construction documents40%$192,000
Construction administration20%$96,000
Total100%$480,000

By the end of construction documents the firm has billed $384,000 - the first four phases, 80 percent of the fee - leaving $96,000 for construction administration. The phase overrun is 240 hours: 1,520 worked less the 1,280 budgeted. At the $150 blended rate that is $36,000 of fee value consumed with no extra fee to bill, and at $95 an hour it is $22,800 of real payroll cost the phase fee has to absorb. The project still bills its full $480,000. It just earns less of it, and the firm learns that from its cash, months later, unless phase hours are tracked against phase fees while the work is still running.

Engineering consultants engaged through the architect create a timing layer of their own. The architect bills the client for consultant work as part of its phase invoice, but the consultant's own invoice arrives on the consultant's schedule, and professional courtesy - and the need to keep good consultants willing to join the next project - pushes the architect to pay before the client has paid. On a consultant-heavy project, that float can reach tens of thousands of dollars. Reimbursables behave similarly at smaller scale: printing, travel, model making, and permit fees go out as they are incurred and come back only when they appear on an invoice the client pays. None of these amounts decide the firm's year. Together, they decide several payrolls.

Try it in Excel: the free project pricing calculator template for Excel: cost each role and expense by month, price to a target margin, and see the peak cash the job needs before it pays. No email or sign-up.

Do architecture firms need a fractional CFO?

Many architecture and design firms start looking for a fractional CFO when the real gap is narrower: nobody can say, with confidence, how much of each fee is earned, how much is billed, and when the cash arrives. A fractional CFO is a part-time senior finance leader. Firms hire one for banking relationships, ownership transitions, pricing strategy and leading a finance team. That is real work, and some firms need it.

The numbers underneath are a different job. Phase-level fee tracking, utilization against fee budgets, a rolling cash forecast and a monthly view of which projects are slipping is FP&A work, and it is what most firms in the $5M to $50M range are missing first. Mesfonic does that part, as fixed-fee projects or a monthly service. It does not act as a CFO, controller or bookkeeper, and it is not a CPA firm. If you are weighing the two, the fractional CFO vs outsourced FP&A guide sets out who does what, and how much a fractional CFO costs covers typical pricing.

Which service fits first

Start with a liquidity review, $950 fixed fee. It maps unbilled work by phase, compares fees billed against work performed on each live project, and ages the receivables behind them. For a design firm, that single picture usually finds the cash: phases drawn ahead of the work, invoices that should have gone out, and one over-running phase that needs a fee conversation now rather than at close-out.