Clearline Projects (fictional)
Month: November 2026 (fictional)
Forecast vs actual - November 2026 (fictional)
| Line | Forecast | Actual | Variance | Variance % |
|---|---|---|---|---|
| Revenue | $420,000 | $385,000 | -$35,000 | -8.3% |
| Direct labor | $180,000 | $192,000 | +$12,000 | +6.7% |
| Subcontractors | $110,000 | $98,000 | -$12,000 | -10.9% |
| Materials | $45,000 | $51,000 | +$6,000 | +13.3% |
| Gross profit | $85,000 | $44,000 | -$41,000 | -48.2% |
| Overhead | $38,000 | $36,000 | -$2,000 | -5.3% |
| Operating profit | $47,000 | $8,000 | -$39,000 | -83.0% |
Check: forecast gross profit is $420,000 minus $180,000 minus $110,000 minus $45,000 = $85,000 (20.2 percent of revenue). Actual gross profit is $385,000 minus $192,000 minus $98,000 minus $51,000 = $44,000 (11.4 percent). Operating profit is gross profit minus overhead: $85,000 minus $38,000 = $47,000 forecast, and $44,000 minus $36,000 = $8,000 actual.
Commentary, line by line
Revenue, -$35,000. One milestone on Willow Creek Fit-Out was billed in the first week of December instead of the last week of November. The work was complete; the client sign-off took four extra days. This is a timing variance and it reverses next month. It is not lost revenue, but it is the reason cash closed at $485,000 instead of the forecast level.
Direct labor, +$12,000. Harbor Point Phase 2 used more senior hours than planned to recover a two-week schedule slip. The hours were real and the recovery worked, but the cost stays in the project: its cost to complete was raised by $30,000 in the EAC review, which is why forecast portfolio margin moved from 13.1 percent to 12.4 percent.
Subcontractors, -$12,000. A subcontractor package on Northgate Systems Upgrade started two weeks late, so its November billing did not arrive. The cost is delayed, not saved. It lands in December, and the December forecast has been raised by the same $12,000 so the saving does not get spent twice.
Materials, +$6,000. Elm Street Renovation needed replacement material after a delivery was damaged on site. The supplier claim is open. Until it settles, the $6,000 stays in project cost and out of any recovery assumption.
Overhead, -$2,000. A planned software renewal moved to December. Timing only, with no change to the annual overhead run rate.
The month in one line. Gross profit fell $41,000 short: $35,000 of revenue timing, plus $18,000 of extra labor and materials, partly offset by $12,000 of delayed subcontractor cost. Only the labor and materials portion, $18,000 gross, is a real margin event; the rest moves between months.