Project S-curve calculator

How a contract earns out month by month under four curve shapes, what billing looks like behind a lag, and the peak of work done but not yet billed. Runs in your browser; nothing is stored or sent.

Your numbers
Months between earning value and billing it
Cash on hand that can fund the unbilled gap

Results update as you type. Method: each month gets a weight from the curve shape, and weights are normalized so they sum to the contract value. Even splits the contract equally. Front-loaded weights fall in a straight line, back-loaded weights rise in a straight line, and the bell (S-curve) weights follow a sine hump, sin(pi x (month - 0.5) / months). Billing in a month equals the value earned the number of lag months earlier.

Your project S-curveEstimate
Peak unbilled work-
Peak month-
Billed by end of the work-
Unbilled above opening cash-

Enter your numbers to see the result.

How it works

Each month earns a share of the contract set by the curve shape, using the weights described above. Billing trails earning by the lag, so cumulative billed is always behind cumulative earned while work is running. Peak unbilled work is the largest gap between the two cumulative lines: the most work done but not yet billed. It is a ceiling on exposure, not the cash need itself - the cash the firm actually puts up is the cost share of that work, less any deposit, plus the wait for payment after each invoice goes out. The project cash curve calculator models cost, deposit and payment lag for the cash view.

Worked example with the default numbers: a $1,200,000 contract over 10 months on the bell (S-curve) shape with a 1-month billing lag. The biggest earning months are months 5 and 6 at about $185,410 each (15.5% of the contract), and because billing runs one month behind, the unbilled position peaks at about $185,410 in month 5. By the end of month 10, about $1,170,634 has been billed and the last month of earnings bills in month 11. Against opening cash of $100,000, unbilled work above opening cash is about $85,410. These are example numbers, not your projects.

Want the gap inside a full cash forecast?

One project's unbilled peak is manageable until three projects peak in the same month. A 13-week cash flow forecast stacks every project's earning and billing curve against payroll and payables, week by week. $2,900 fixed fee.