Estimate at completion (EAC)

Estimate at completion is your current best forecast of what a job will cost in total when it is finished.

What it is

Estimate at completion, usually shortened to EAC, is the total cost you now expect a job to carry when the last invoice, timesheet and delivery note are in. It is not the original budget. The budget is what you hoped or planned at the start. The EAC is what the evidence says today, after some costs are already spent and the remaining work is clearer than it was on day one.

Project businesses live or die on this number because so many other numbers depend on it. Percent complete uses it. Earned revenue uses it. The margin you report this month uses it. If the EAC is stale or optimistic, all of those figures are wrong in the same direction, and the error only surfaces at the end of the job, when there is no time left to fix it.

The formula

Stated plainly: EAC equals cost incurred to date plus estimate to complete. Cost incurred is what has already been spent on the job. Estimate to complete, or ETC, is a fresh estimate of what the work still to be done will cost. Add the two together and you have the total cost you expect at finish.

A second check is useful. Compare the EAC with the original budget. The difference is the forecast variance on the job. A positive gap, where the EAC sits above budget, means the job is expected to overrun. A gap the other way means it is expected to finish under budget. Neither result is good or bad on its own until you know why it moved.

How to calculate it

Start with cost incurred from the job cost ledger, not from memory, and make sure recent supplier invoices and timesheets are included. Then rebuild the estimate to complete from the remaining work itself: list what is left to do, price the labor, materials and outside costs for each part, and add an allowance only where a specific risk is known. Do not simply take the budget minus cost incurred and call the remainder the ETC. That shortcut assumes the original budget was right, which is exactly the thing the EAC is meant to test.

Update the EAC whenever the job changes in a material way: a change order, a delay, a price increase, or a stretch of work that took longer than planned. On an active job, a monthly review is a sensible minimum, tied to the same meeting that reviews the work in progress schedule.

Worked example

Example - fictional numbers. A job was budgeted at $500,000 of total cost. Partway through, the ledger shows $220,000 already spent. The team reprices the work still to be done and puts the estimate to complete at $310,000.

ItemAmount
Original budget$500,000
Cost incurred to date$220,000
Estimate to complete (ETC)$310,000
Estimate at completion (EAC)$530,000
Forecast variance vs budget-$30,000

Step by step: first, add cost incurred and the estimate to complete: $220,000 plus $310,000 equals $530,000. That is the EAC. Second, compare it with the budget: $500,000 minus $530,000 equals -$30,000. The job is now forecast to cost $30,000 more than budgeted. Third, use the EAC for percent complete: $220,000 divided by $530,000 equals about 41.5 percent. If you had kept using the old $500,000 budget as the denominator, you would have shown 44.0 percent complete and overstated progress.

Why it matters and common mistakes

The EAC matters because it turns a surprise at the end of a job into a decision in the middle of it. A $30,000 overrun found early can still lead to a conversation about scope, sequencing or a change order. The same overrun found at close-out is just a smaller margin and a lesson nobody priced.

The common mistakes are consistent. Leaving the EAC equal to the budget for months because nobody repriced the remaining work. Letting the person delivering the job mark their own homework without a challenge. Adding a general contingency to hide a known overrun instead of naming it. And updating the EAC in a spreadsheet but not in the work in progress schedule, so reported revenue keeps using the old number. Keep one EAC per job, in one place, reviewed on a set schedule. For how the EAC feeds billing and revenue, see the guide to WIP schedules and over and under billing, and test the cash effect of a slipping job in the free 13-week cash flow calculator.

For the full method, including how EAC feeds percent complete and margin, see the guide to estimate at completion (EAC) explained.