Estimate at completion (EAC) explained

One formula turns a half-finished project from a guess into a forecast: cost incurred to date, plus what the rest will honestly cost.

Last updated: November 2026

The short version

  • EAC = cost to date + cost to complete. It is your current best estimate of the project's total cost.
  • Forecast profit = contract value - EAC; forecast margin is that profit divided by contract value. Compare it with the target margin from pricing, not with zero.
  • Cost to complete must be estimated from the remaining work, never taken as budget minus spend.
  • Update the EAC monthly. Its movement over time is as informative as its level.

The formula

Estimate at completion is the total cost you now expect a project to carry when it is finished. The formula has two parts:

EAC = cost to date + cost to complete

Cost to date is factual: every direct cost charged to the project so far, including accruals for work that has been done but not yet invoiced to you. Cost to complete is the estimate: what the remaining work will cost from today to the end. Add them and you have the number that decides the project's outcome while there is still time to change it. From the EAC, the rest follows: forecast profit is contract value minus EAC, and percent complete on a cost basis is cost to date divided by EAC.

The EAC matters because the budget cannot do its job. The budget was written before the project met reality. It stays useful as a yardstick - the thing you measure variance against - but it cannot tell you where the project will land. The EAC can, provided the cost to complete inside it is honest.

How to estimate cost to complete

Cost to complete is where EACs succeed or fail, so it deserves a method, not a mood. Build it in four steps:

  • List what is left. Remaining tasks, phases or deliverables, in the same structure as the original estimate where possible.
  • Price each item at real rates. The hours each item needs, at the cost of the people who will actually do it, plus materials, subcontractors and project expenses still to come.
  • Use actual performance so far. If completed work of the same kind cost more per unit than planned, carry that rate into the remaining work unless something specific has changed.
  • Add the tail. Testing, corrections, documentation, handover and closeout are real costs that early estimates routinely underweight.

The shortcut to avoid is budget remaining: original budget minus cost to date. Used as cost to complete, it forces the EAC to equal the budget by construction, so the forecast can never show an overrun until the money is gone. If your EAC never moves, that shortcut is usually why.

Have the estimate made by the person closest to the work and challenged by someone who is not delivering it. Optimism in cost to complete is rarely dishonesty; it is the natural bias of someone who has to stand behind the plan. A short challenge - what could make this cost more, what did the last phase actually cost, what is not on this list - removes most of it.

A worked example

Take a fictional project with a contract value of $600,000, priced on a budget cost of $510,000 - a target margin of $90,000, or 15 percent. Partway through, the position is:

ItemAmount
Cost to date (including accruals)$275,000
Cost to complete: remaining labor$140,000
Cost to complete: materials$60,000
Cost to complete: subcontractors$45,000
Cost to complete: other project costs$20,000
Total cost to complete$265,000
EAC ($275,000 + $265,000)$540,000
Forecast margin ($600,000 - $540,000)$60,000 (10.0%)
Variance vs budget cost ($540,000 - $510,000)$30,000 over

The cost-to-complete lines add to $265,000, so the EAC is $540,000 and forecast profit is $60,000 - a 10 percent margin on contract value against a 15 percent target. On a cost basis the project is 50.9 percent complete ($275,000 divided by $540,000). Now compare the shortcut: budget remaining is $510,000 minus $275,000, or $235,000. Used as cost to complete, it would report an EAC of exactly $510,000 and a margin of exactly $90,000 - a forecast that says the project is perfectly on budget precisely because it assumed so. The honest estimate shows $30,000 of overrun with half the cost still to spend, which is when re-planning, re-pricing or a scope conversation can still recover some of it. This example is fictional and the figures are illustrative.

Run an EAC on your own projectThe free project profitability calculator takes cost to date and cost to complete and returns the EAC and forecast margin, so you can test the method on a live project in minutes.

Reading the EAC over time

A single EAC is a forecast. A series of EACs is a diagnosis. Keep each month's figure and watch the pattern. A stable EAC while cost to date rises means cost to complete is falling at the same pace - the project is consuming its remaining work as planned. An EAC that rises month after month means the estimates are chasing reality: each month's cost to complete was too low, and the correction is arriving in installments. An EAC that jumps once, with a named cause - a scope change, a failed component, a rate increase - is usually healthier than one that creeps, because the cause can be priced, discussed or fixed.

The EAC also feeds two other views. Placed by week, the cost to complete becomes the spending side of your cash forecast; our guide to tracking project profitability shows how the monthly review ties the two together. And summarized across projects, EAC margin is one of the core figures on the dashboard described in our guide to financial dashboards for project-based firms.

EAC in different industries

The formula does not change, but the cost-to-complete estimate is built differently by sector. In EPC and engineering, much of the remaining cost sits in bought-in packages and subcontract commitments, so the estimate leans on committed prices plus allowances for what is not yet bought. In architecture and design, remaining cost is mostly hours through design development, documentation and construction-phase services, so the estimate leans on staffing plans and phase completion. Either way, the discipline is identical: estimate the work that remains, at the rates reality has shown you, and never let the budget do the estimating for you.

When a lender or board is watching, the EAC sits inside the reporting pack rather than replacing it. Our board and lender reporting service, from $1,500/month, presents project forecasts alongside cash and covenant reporting in a consistent monthly format.

Common questions

What is the formula for estimate at completion?

EAC equals cost to date plus cost to complete. Cost to date is the cost the project has incurred, including accruals for work done but not yet invoiced to you - not the cash paid out, which is a separate timing question. Cost to complete is a bottom-up estimate of what the remaining work will cost. Forecast profit is then contract value minus EAC, and forecast margin is that profit as a share of contract value.

What is the difference between EAC and the project budget?

The budget is what you planned to spend when the project was priced. The EAC is what you now expect to spend, given everything learned since. Early in a project they may be close; as real costs arrive, the EAC should move with the evidence while the budget stays as the original yardstick.

How often should the EAC be updated?

Monthly, alongside the project profitability review, and immediately when scope, schedule or staffing changes in a way that affects remaining cost. An EAC that only changes at the end of the project is not a forecast; it is a delayed actual.

Can the EAC be lower than cost to date?

No. The EAC includes everything already spent, so it can never fall below cost to date. If a calculation produces that, the cost to complete has been set to a negative number, which usually means budget remaining was used instead of a real estimate of the remaining work.

Try it in Excel: the free project profitability tracker for Excel: estimate at completion, margin against target, over and under billing and margin leakage for up to 30 projects. No email or sign-up.

Keep reading

General information, not advice for your specific situation.