Change orders and cash

Work your team has already done, the client has not approved, and nobody has billed: what it costs, and the discipline that stops it.

Last updated: November 2026

The short version

  • An unapproved change order is work performed with no enforceable right to bill it. The cost is real and paid; the revenue is a hope.
  • Unbilled change work inflates WIP and unbilled revenue, so the balance sheet looks healthier than the bank account.
  • The fix is a signature before the work starts, a register that lists every change order, and a short weekly review that ages them.
  • Price the delay: every month a change order sits unbilled, your firm is lending the client money at your credit line rate.

How change orders leak cash

The pattern is familiar in every project-based firm. The client asks for something outside the agreed scope, usually verbally, usually in a meeting where saying no feels expensive. A project manager wants to keep the relationship warm and the schedule moving, so the team does the work. The paperwork will follow, everyone agrees. Then the paperwork does not follow. The person who asked has no authority to approve the spend, or their budget cycle has closed, or they simply dispute that the work was extra at all. Weeks pass. The hours sit in WIP, unbilled, while the salaries that produced them left the bank account on the normal payroll dates.

Notice what has happened in cash terms. Your firm has made the client an unsecured loan, at no interest, with no signed note, for an amount the client has not agreed it owes. No firm would approve that loan if it arrived as a loan request. It arrives instead as helpfulness, one small request at a time, which is why the total is usually a surprise when someone finally adds it up. Our guide to unbilled revenue and WIP covers the wider unbilled problem; change orders are its most preventable part, because every one of them passed through a moment where a signature was possible.

What unapproved work does to WIP

WIP, work in progress, is where unbilled work accumulates. Contracted work in WIP is normal: it bills on the next cycle or at the next milestone. Unapproved change work in WIP is different, because there is no agreed billing event coming. It ages silently. A WIP schedule that mixes the two hides the problem inside a total that looks like ordinary timing, which is why the WIP schedule should always split unbilled balances into contracted work awaiting its billing date and change work awaiting approval. The second bucket deserves its own line, its own owner and its own aging.

The accounting flatters the firm while the cash suffers. Depending on how the firm recognizes revenue, unapproved work may sit in unbilled revenue at full value, supporting a profit figure the bank balance cannot confirm. Lenders and buyers read WIP schedules closely for exactly this reason: a growing unbilled balance with aging change orders inside it reads as revenue quality risk, and it can surface at the worst possible moment, during a credit review or a sale process.

Worked example: one quarter of unsigned change work

Take a fictional firm billing $300,000 per month, or $3,600,000 a year. In one quarter, its teams perform 8 change orders without signed approval, at an average billing value of $12,000 each.

Step 1: value the work. 8 x $12,000 = $96,000 of work performed and unbilled.

Step 2: calculate the cash already spent. Direct labor and costs run at 60 percent of billing value, so the firm has already paid out 0.60 x $96,000 = $57,600 in payroll and project costs. That money is gone regardless of what happens next.

Step 3: watch the WIP balance. In a normal month the firm carries about 15 days of unbilled contracted work: $300,000 / 30 days x 15 days = $150,000. Add the unapproved change work and the unbilled balance reaches $150,000 + $96,000 = $246,000, a 64 percent increase, with the increase concentrated in the bucket that has no billing date.

Step 4: price the delay. With prompt approval, this work would bill in the next monthly run and collect about 45 days after the work was done. In the event, approval takes 60 days, the work bills in the following run, and the client pays on net 30 terms, so cash arrives around day 105, roughly 60 days late. If the firm funds the gap on a credit line at 8 percent, the carrying cost on $96,000 for 60 extra days is $96,000 x 0.08 x 60 / 365 = $1,262. Small on its own; repeated every quarter, the same habit puts $96,000 x 4 = $384,000 of work a year through the slow lane.

Step 5: count the loss when approval never comes. Suppose 2 of the 8 change orders, worth $24,000, are refused outright. The revenue never exists, and the sunk cost is 0.60 x $24,000 = $14,400 of payroll paid for work nobody will reimburse. That is the true price of the unsigned quarter: $14,400 written off, $1,262 of interest on the rest, and $57,600 of cash that spent two extra months outside the business.

Run your own numbersThe free WIP over and under billing calculator shows how much of your unbilled balance is ahead of or behind billings, project by project.

Approval discipline that actually holds

Discipline fails when it depends on project managers choosing paperwork over relationships in the moment. It holds when the firm sets the rule once, in writing, and builds it into the engagement terms every client signs. Three elements do most of the work.

A signature rule with a narrow emergency exception

No change work starts without written approval stating the scope and the price. The single exception is a defined emergency category, capped at a small dollar amount per event, which the project manager can authorize and must document the same day. Everything else waits for the signature. Clients respect the rule when it is in the contract they signed and applied the same way to everyone; they resent it when it appears improvised, mid-project, for them alone.

A named approver on the client side

At project kickoff, record who on the client side can approve change orders and up to what amount. Half of all approval delays are authority problems: the person asking cannot sign, and the person who can sign hears about the work for the first time on the invoice. Naming the approver in advance turns a dispute into a routing question.

A stop-work trigger

Agree that when unapproved change work on a project passes a set value, further change work pauses until approvals catch up. The trigger protects the project manager, who no longer has to make the call personally; the rule makes it.

One more rule completes the discipline: bill approved change orders in the next billing run, every time, without waiting for the project to finish. A signed change order that sits unbilled for two months has the same cash effect as an unsigned one. Approval fixes the right to bill; only the invoice fixes the cash, and the client's payment clock does not start until the invoice exists.

A simple tracking method

You do not need software for this. A single register, one row per change order, reviewed weekly, covers it. Give each change order a number and record: project, description, date requested, billing value, estimated cost, date sent for approval, approver name, status (requested, priced, awaiting signature, approved, billed, refused), date billed and date paid. Two habits make the register work. First, the project manager updates it before the weekly review, not after. Second, the review looks at aging, not just totals: any item awaiting signature for more than 14 days gets a named follow-up that week, and any item older than 45 days gets escalated to a principal. The register also feeds billing directly, so approved items never wait for someone to remember them at month end.

Tie the register to the forecast and the discipline pays for itself twice. A 13-week cash flow forecast should only count change order receipts once approval is signed; unsigned work stays out of the receipts line and on the risk list. If your WIP and receivables need a full diagnosis rather than a single fix, that breakdown is the core of our liquidity review: a fixed $950 review that values each blockage in cash and ranks the actions. Firms that want the register, the WIP split and the forecast maintained every month usually fold it into outsourced FP&A, from $2,500/month.

Common questions

Should we ever start change order work before approval?

Only under a written emergency rule with a small dollar cap, agreed in the contract in advance. Genuine emergencies exist: work that protects safety, a permit or a hard deadline. Everything else can wait the day or two a signature takes. If the client will not sign, that tells you how the invoice would have gone.

Does an email approval count as a signed change order?

An email from the person authorized to approve, stating the scope and the price, is far better than a verbal yes and is what most small firms realistically collect. The weak point is authority: make sure the person approving can actually commit the client's budget, and confirm that in the engagement terms at the start.

How do unbilled change orders affect our financial statements?

The labor cost lands in WIP or cost of services right away, while the revenue often cannot be recognized until approval makes collection probable. The result is inflated unbilled balances, margin that looks worse than the underlying work, and awkward questions from a lender reading the WIP schedule.

What should we do about old unapproved change orders already sitting in WIP?

List them, age them, and work the list in a single cleanup: get signatures where the relationship supports it, bill what is approved, and write off the rest honestly. Carrying hopeless balances forward does not preserve value; it hides a loss and distorts every WIP report until you clear it.

How many change orders should we review each week?

All of the open ones. In a small or mid-size firm the register is usually a page or two. The weekly review takes fifteen minutes when the register is current, and it is the meeting that keeps small approvals from aging into write-offs.

Try it in Excel: the free project profitability tracker for Excel: estimate at completion, margin against target, over and under billing and margin leakage for up to 30 projects. No email or sign-up.

Keep reading

General information, not advice for your specific situation.