The short version
- Working capital for a project firm is mostly three balances: unbilled work, receivables and retainage, minus payables.
- Measure each balance in days so you can see which one is growing and what a day is worth in cash.
- Overbilling is borrowed cash from clients; underbilling is a loan you are making to them. Both belong in the working capital picture.
- The release levers are billing speed, collection speed and payment timing - in that order of control.
Why project firms are different
A trading business ties cash up in inventory: it buys stock, holds it, sells it. A project-based firm barely holds stock at all. Its cash is tied up in time - the gap between doing work and being paid for it. That gap has three distinct stretches, and each stretch is a separate balance with a separate owner inside the firm. Work is performed but not yet billed: that is unbilled revenue, sometimes sitting inside the work-in-progress (WIP) schedule. Work is billed but not yet paid: that is accounts receivable. And a slice of every billing is held back by the client as retainage until contract conditions are met: that is retainage receivable, the slowest money in the building. Against those, the firm holds one offsetting balance: payables, the bills it has not yet paid its suppliers and subcontractors.
This is the working capital that project-based FP&A manages week to week. It behaves differently from inventory in one important way: none of it is visible on a shelf or in a warehouse count. It only exists in schedules - the WIP schedule, the receivables ageing, the retainage listing - which is why it so often grows unnoticed. A firm can be profitable on every project and still run out of cash because the three stretches lengthened by a few days each. A few days sounds small. At scale, a day is a large amount of money, as the worked example below shows.
The four balances, in days
Convert each balance to days so the balances can be compared and tracked. Days sales outstanding (DSO) is receivables divided by annual revenue, times 365. Unbilled days is unbilled revenue divided by annual revenue, times 365. Retainage days uses the same revenue base. Days payables outstanding (DPO) is payables divided by annual direct costs, times 365 - payables scale with what the firm buys, not what it sells, so the cost base is the honest denominator. Net working capital days is DSO plus unbilled days plus retainage days, minus DPO. That single number is the length of the firm's cash cycle in its project form: how many days of activity the firm funds out of its own pocket.
Days also price the levers. One day of DSO or unbilled work is worth annual revenue divided by 365. One day of DPO is worth annual direct costs divided by 365. The free working capital release calculator does exactly this arithmetic for your own targets, lever by lever. The point of the days view is diagnostic: when cash tightens, it tells you which stretch lengthened, instead of leaving you staring at a bank balance and a feeling.
Overbilling and underbilling are working capital too
Billing position - the difference between what a project has billed and what it has earned - is working capital wearing a project costume. An overbilled project has collected, or at least billed, ahead of the work: the excess is effectively an interest-free loan from the client, and it flatters firm cash while it lasts. An underbilled project has earned more than it has billed: the firm has funded the client's project out of its own cash, and the underbilling balance is unbilled work in its least liquid form, because it cannot even start the collection clock until it is billed.
Two disciplines follow. First, never read a healthy bank balance without the billing position beside it: a firm can look liquid purely because two large projects are overbilled, and that cash is spoken for by work still to be performed. Second, treat growing underbillings as a working capital problem, not an accounting footnote. Underbilling grows for operational reasons - milestones not certified, paperwork incomplete, project managers reluctant to bill - and every week of delay is a week the firm lends money to its clients for free. Our guide to the WIP schedule and over and under billing covers the project-level mechanics.
A worked example
Take a fictional firm with annual revenue of $18,250,000 - exactly $50,000 of revenue per day - and annual direct costs of $14,600,000, or $40,000 per day. Its balances are:
| Balance | Amount | Days |
|---|---|---|
| Accounts receivable | $2,700,000 | 54 days of revenue |
| Unbilled work | $900,000 | 18 days of revenue |
| Retainage receivable | $600,000 | 12 days of revenue |
| Accounts payable | -$1,200,000 | 30 days of direct costs |
| Net working capital tied up | $3,000,000 | - |
The firm has $3,000,000 of its own cash funding its clients' projects: $2,700,000 + $900,000 + $600,000 - $1,200,000. Now price three modest moves. Collecting 6 days faster releases 6 x $50,000 = $300,000. Billing 5 days faster releases 5 x $50,000 = $250,000. Paying 5 days later releases 5 x $40,000 = $200,000. Together: $750,000 of cash, released once, without selling anything extra or raising prices - purely from timing settings the firm already controls to a large degree. Retainage is deliberately left out of the lever list: its release is governed by contract conditions and client processes, so it is managed by tracking and chasing, not by internal settings. This example is fictional and the figures are illustrative.
Which lever to pull first
Sequence by control. Billing speed is the most fully internal lever: invoices wait on the firm's own paperwork, certifications and habits, so unbilled days usually fall fastest. Collection speed is next: it depends on clients, but disciplined invoicing accuracy, prompt follow-up and clear escalation move it. Payment timing is last, not because it is small but because it spends supplier goodwill, and because stretching subcontractors can create risks that a few days of cash do not justify - a theme our guide to DPO and subcontractor terms takes up directly. Firms in engineering consulting tend to find their largest balance in unbilled work; firms in construction tend to find it in retainage. The days table tells you which firm you are.
Whatever the sequence, measure monthly and in days. Balances in dollars grow with the firm and hide the trend; days strip out growth and show whether the cycle itself is lengthening. When days creep two months in a row, something operational changed - find it while it is still a process problem and not yet a cash problem. Firms that want this measured and chased for them use our liquidity review, $950 fixed fee, which breaks the balances down by customer, project and supplier and ranks the release levers by cash impact.
Common traps
- Judging liquidity by the bank balance. Overbilled projects can make a strained firm look comfortable. Always read cash beside billing position.
- Treating retainage as ordinary receivables. It follows contract conditions, not invoice terms. Age it separately and chase releases as their own workflow.
- Chasing DSO while unbilled work balloons. Collecting billed invoices faster does nothing for work that has not been billed. The clock starts at the invoice.
- Counting a one-time release as recurring improvement. Released cash arrives once. Holding the new days level keeps it; it does not release it again next year.
Reading the three stretches together
The balances also interact, and the interactions are where surprises live. Faster billing, for example, does not release cash by itself: it moves value from the unbilled balance into receivables, where the collection clock takes over. The firm's total working capital only falls when the billed invoice is actually paid sooner than the work would otherwise have converted. That is why the days table must be read as a chain - unbilled days plus DSO is the true work-to-cash distance for billed work - rather than as three independent scores to be optimized separately. A firm that cuts unbilled days from 18 to 10 while DSO drifts from 54 to 62 has rearranged its working capital, not released it.
Retainage interacts differently: it grows automatically with billings on retainage-bearing contracts, so a firm can do everything right on billing and collections and still watch total working capital climb because its contract mix shifted toward retainage-heavy work. The planning consequence is that working capital targets should be set per balance and in total, and reviewed against contract mix, not just against last month. When a large retainage-bearing project is signed, the working capital forecast should move the day the contract is signed - months before the balance itself does.
Common questions
What counts as working capital in a project-based firm?
Mainly unbilled work (revenue earned but not yet billed), accounts receivable, and retainage receivable, minus accounts payable. Inventory is usually minor. Measured in days against revenue - and payables against direct costs - these balances show how much of its own cash the firm uses to fund client work.
Is overbilling good for cash?
Temporarily, yes: an overbilled project has billed ahead of work performed, so client money funds the firm. But that cash is owed as future work, and when the project catches up the funding unwinds. A firm that depends on overbilling to feel liquid is borrowing from its own backlog.
Why measure working capital in days instead of dollars?
Dollars grow as the firm grows, which hides whether the cycle is actually lengthening. Days strip out scale: if DSO moves from 50 to 56 while revenue is flat or growing, collections genuinely slowed, and the dollar value of the slippage is days moved times revenue per day.
How much cash can working capital changes really release?
More than most owners expect. In the worked example, a mid-size firm releases $750,000 from three modest moves - 6 days of collections, 5 days of billing, 5 days of payments. The release is one-time, not recurring, but it is real cash for paying down a line or funding growth.
Keep reading
Unbilled revenue and WIP
GuideRetainage and cash flow
Free toolWorking capital release calculator
Free toolCash conversion cycle calculator
General information, not advice for your specific situation.
Rather have the levers ranked for you?
A liquidity review that sizes every working capital lever from your own ledger and ranks the moves by cash impact. $950 fixed fee.
Prefer email? hello@mesfonic.com
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.