The short version
- Percent complete is an estimate of how much of a project is done. One common measure divides cost incurred so far by the total cost expected at completion.
- Revenue recognized is the contract price multiplied by that percentage. Progress drives revenue; the invoice schedule does not.
- Billings follow the contract's payment terms, so they usually differ from revenue. The difference is the overbilled or underbilled position.
- When the total cost estimate changes, the percentage and the revenue move with it - which is the point of the method.
A plain note before the concepts. This page is general information that explains ideas, in plain language, so owners can read their reports and follow discussions with their advisors. It is not accounting advice, it does not describe how any specific contract should be treated, and it is not a substitute for your accountant's judgment on your own facts. Revenue recognition rules are detailed and fact-specific; this guide deliberately stays at the level of concepts.
The problem the idea solves
Imagine a project that runs for fourteen months. The work starts in one financial year and ends in the next. If the firm counted revenue only when the project finished and the final invoice went out, the first year would show all of the project's costs and none of its revenue, and the second year would show a large revenue figure with few costs left against it. Both years would mislead anyone reading them - an owner judging performance, a lender judging the business, a buyer judging what the firm earns. The percent-complete idea exists to spread the contract price across the periods in which the work is actually done, so that revenue and the costs of earning it land in the same periods. It is one of the foundational concepts behind the reporting model in our overview of FP&A for project-based firms.
The matching intuition is simple: a project that is a third done has, in economic substance, earned roughly a third of its price - even if the contract lets the firm bill nothing until a milestone, or bill half up front. Percent-complete turns that intuition into arithmetic.
The three ingredients
The calculation needs three numbers. The first is the contract price: what the client has agreed to pay for the work, including approved change orders. The second is cost to date: what the project has actually cost so far. The third is the estimated total cost at completion - cost to date plus an honest estimate of the cost still to come. That third number is where judgment lives, and it is the same estimate that drives the estimate at completion used in project margin tracking. An optimistic total-cost estimate does not just flatter the margin; under this method it also pulls revenue forward, which is why the estimate deserves challenge from someone other than the person delivering the project.
With those three numbers, the concept runs in two steps. Percent complete is cost to date divided by estimated total cost. Revenue recognized to date is the contract price multiplied by that percentage. Revenue for the current period is the new cumulative figure minus whatever was recognized in earlier periods - a catch-up each period, rather than a fresh guess, so corrections to earlier estimates flow through the current period's number.
Revenue, billings and cash are three different clocks
Most confusion around this topic comes from treating three separate things as one. Revenue follows progress, as described above. Billings follow the contract's invoicing terms: deposits, milestone invoices, monthly applications, holdbacks - whatever the contract says, on whatever dates it says. Cash follows the client's payment behavior after the invoice. On any given date the three figures for the same project can be far apart, and none of them is the "real" one; each answers a different question.
The gap between revenue and billings has names you will see on a WIP schedule. When billings run ahead of revenue recognized, the project is overbilled: the firm has invoiced for more than it has earned, and in substance it holds client money against work still to do. When revenue runs ahead of billings, the project is underbilled: the firm has earned more than it has invoiced, and in substance it is financing the client's project until billing catches up. The free WIP over and under billing calculator works through that comparison for a single project. Neither position is automatically good or bad - contracts are written both ways - but a large, growing underbilled position deserves attention, because earned-but-unbilled work is the easiest revenue to argue about later.
A worked example, concepts only
Take a fictional project with a contract price of $500,000 and an estimated total cost of $400,000 - an expected profit of $100,000 if the estimate holds. Partway through, cost to date is $150,000. The concepts produce:
| Item | Amount |
|---|---|
| Contract price | $500,000 |
| Estimated total cost at completion | $400,000 |
| Cost to date | $150,000 |
| Percent complete ($150,000 / $400,000) | 37.5% |
| Revenue recognized to date ($500,000 x 37.5%) | $187,500 |
| Gross profit to date ($187,500 - $150,000) | $37,500 |
| Billings to date (per contract terms) | $160,000 |
| Underbilled position ($187,500 - $160,000) | $27,500 |
Notice what the example shows. The project has earned $187,500 by progress, billed only $160,000 by its contract terms, and spent $150,000 - three different numbers, all correct, each answering its own question. Profit to date is $37,500, which is exactly 37.5 percent of the expected $100,000 total profit: the method spreads profit in proportion to progress as long as the cost estimate holds. Now change one fact: suppose the remaining work is re-estimated and total cost becomes $440,000 instead of $400,000. The same $150,000 of cost to date is now 34.1 percent of the total, recognized revenue steps back to about $170,500, and expected total profit falls to $60,000. Nothing about the past changed; the estimate of the future did, and the revenue line absorbed the news immediately rather than at completion. That sensitivity is a feature to understand, not a flaw to be surprised by. This example is fictional, simplified, and illustrative of the concepts only.
Where judgment and risk sit
Because revenue under this method rests on an estimate of total cost, the quality of the revenue figure can never exceed the quality of that estimate. Three habits protect it. Re-estimate total cost on a regular cycle, from the remaining work upward, rather than carrying the original budget forward by default. Keep the people who estimate completion cost close to the work but reviewed by someone without a stake in the answer. And treat sudden improvements in percent complete with the same skepticism as sudden deteriorations: both usually mean the denominator moved, and the reason should be nameable - a scope change, a productivity change, a price change - before the new figure is relied on.
It also helps to know the limits of the cost-based measure itself. Cost incurred does not always track progress neatly: materials bought early and sitting on site can push cost ahead of actual accomplishment, and inefficient work spends cost without creating progress. Firms and their accountants deal with wrinkles like these in the detailed application of the method, which is one more reason this guide stays at concept level. What an owner needs is the ability to ask the right questions - what is our total cost estimate based on, when did it last change, and why - and to recognize that a WIP schedule is an estimate with a structure, not a count of facts.
For firms in specialty and MEP contracting and other long-project trades, these concepts show up every month in the WIP schedule that lenders and bonding companies read, so fluency in them pays off in those conversations. Where a board or lender relies on the figures, presentation matters as much as the arithmetic; our board and lender reporting service, from $1,500/month, keeps WIP, margins and cash in one consistent monthly pack. To repeat the note from the top: this page is general information, not accounting advice, and your own treatment should be settled with your accountant.
Common questions
What does percent complete mean in plain terms?
It is an estimate of how much of a project is done, expressed as a percentage. In the cost-to-cost version, it is the cost incurred so far divided by the total cost the project is expected to carry when finished. If a project has spent $150,000 of an expected $400,000 total cost, it is 37.5% complete on that measure.
Why is revenue different from billings on a long project?
Because they follow different clocks. Revenue follows progress: work done earns its share of the contract price. Billings follow the contract's invoicing terms, which may run ahead of progress or behind it. The gap between the two is what overbilled and underbilled positions describe.
What happens to percent complete when the total cost estimate changes?
The percentage is recalculated using the new total. If expected total cost rises, the same cost to date becomes a smaller percentage of a bigger whole, so recognized revenue steps back and margin shrinks. That is the mechanism working as intended: bad cost news reaches the revenue line early instead of at completion.
Is this guide enough to set my firm's revenue policy?
No. This guide explains the concepts in general terms so you can follow the conversation and read your own reports. How the method applies to your contracts, and which treatment your financial statements require, are questions for your accountant, who can see your specific facts.
Try it in Excel: the free project profitability tracker for Excel: estimate at completion, margin against target, over and under billing and margin leakage for up to 30 projects. No email or sign-up.
Keep reading
Unbilled revenue and WIP
GuideWIP schedules and over and under billing
GuideEstimate at completion (EAC) explained
Free toolWIP over and under billing calculator
General information, not advice for your specific situation.
Rather have it built for you?
Board and lender reporting that keeps WIP, project margins, cash and covenants in one consistent monthly pack. From $1,500/month.
Prefer email? hello@mesfonic.com
Mesfonic is not a CPA firm. It does not provide audit, review, attest, tax, legal or investment services, and nothing on this site is professional advice for your specific situation.
Forecasts and analyses are estimates based on the information you provide. Actual results will differ.